ERP Area: Workforce Management (Time & Labor Management)
Software: UKG Pro Workforce Management
Products Implemented: Payroll
Company Size: 5 – 10k Employees / Industry: Healthcare / Medical
Regions in Scope: North America
Reviewer Role: Project Leader
Consultant Recognized: Amy Whipkey
Project(s) in Scope: Initial deployment (Phase 1)
Systems Expertise 5 out of 5
Implementation Process 5 out of 5
Responsiveness 5 out of 5
Quality of Consultants 5 out of 5
Flexibility / Adaptability 5 out of 5
SPEED & COST
Speed vs. Expectations: 1.25x the time we expected
Cost vs. Expectations: Exactly what we budgeted
SCOPING ACCURACY:
How well did your implementation partner scope the work and understand your needs during the pre-sales process?
Partner scoped and quoted the work well, but our needs changed during implementation
Was the implementation team who actually performed the work the same team that was proposed?
Slight change in team
What “Lessons Learned” would you provide to others implementing with this partner / software? What else would you tell us about your project experience?
MetroHealth fell behind on testing which compressed all downstream testing cycles, so the delay was on us.
HyBridge was flexible which is allowing us to stay on target for our cutover date of Sunday, October 26th with a system-wide Go-Live the following day.