ERP Area: ERP, Financials
Software: Unit4
Products Implemented: Financials
Company Size: 250 – 499 Employees / Industry: Professional Services
Regions in Scope: Central Europe
Reviewer Role: Project Leader
Consultant Recognized: Manoah van Teefelen
Systems Expertise 4 (out of 5)
Implementation Process 3 (out of 5)
Responsiveness 3 (out of 5)
Quality of Consultants 4 (out of 5)
Flexibility / Adaptability 4 (out of 5)
SPEED & COST
Speed vs. Expectations: Right on schedule!
SCOPING ACCURACY:
How well did your implementation partner scope the work and understand your needs during the pre-sales process?
Partner did not identify issues that came up during implementation and we had some change orders
Was the implementation team who actually performed the work the same team that was proposed?
No change
What “Lessons Learned” would you provide to others implementing with this partner / software? What else would you tell us about your project experience?
The implementation is going according to schedule. The steps of the process are clear and set up in a reasonable time frame. The structure and scope of planning could be more extensively.