ERP Area: Workforce Management (Time & Labor Management)
Software: UKG Pro Workforce Management
Products Implemented: UKG Kronos
Company Size: 1 – 5k Employees / Industry: Manufacturing
Regions in Scope: North America
Reviewer Role: Project Leader
Consultant Recognized: Goran Matic, Michael Morgan
Project(s) in Scope: Add-on deployment (Phase 2, and not in the original SOW),Training
Systems Expertise 5 out of 5
Implementation Process 5 out of 5
Responsiveness 5 out of 5
Quality of Consultants 5 out of 5
Flexibility / Adaptability 5 out of 5
SPEED & COST
Speed vs. Expectations: Right on schedule!
Cost vs. Expectations: Exactly what we budgeted
SCOPING ACCURACY:
How well did your implementation partner scope the work and understand your needs during the pre-sales process?
Partner scoped and quoted the work well, but our needs changed during implementation
Was the implementation team who actually performed the work the same team that was proposed?
No change
What “Lessons Learned” would you provide to others implementing with this partner / software? What else would you tell us about your project experience?
1. Badge compatibility assessment should have been conducted during the scoping and planning phase
2. Support hours for Configuration and Testing should have been better planned with buffer.