ERP Area: ERP, Financials
Software: Unit4
Products Implemented: Unit4 ERP
Company Size: 1000 – 4999 Employees / Industry: Professional Services
Regions in Scope: Asia / Pacific
Reviewer Role: Project Leader
Consultant Recognized: Chris Develin, Richard Maxfield, Hans Snel
Systems Expertise 4 (out of 5)
Implementation Process 3 (out of 5)
Responsiveness 5 (out of 5)
Quality of Consultants 4 (out of 5)
Flexibility / Adaptability 4 (out of 5)
SPEED & COST
Speed vs. Expectations: 1.25x the time we expected
Cost vs. Expectations: 1.5x cost budgeted
SCOPING ACCURACY:
How well did your implementation partner scope the work and understand your needs during the pre-sales process?
Partner under-quoted the project and we had multiple change orders
Was the implementation team who actually performed the work the same team that was proposed?
Team changed a lot
What “Lessons Learned” would you provide to others implementing with this partner / software? What else would you tell us about your project experience?
Overall is ok as the project was delivered with a tight schedule of 8 months. Some Agilyx consultants were really good and some were not as experienced. Although most key functionalities were delivered, the original demo set a high expectation which couldn’t be met in reality due to the tight schedule.